Last updated on: 14 February, 2026

चल रही क्षमता संवर्धन परियोजनाएं

Sl. No.Name of the ProjectEstimated Cost(Rs. Cr.)Status
1Development of Western Dock on BOT basis to handle Cape size vessels.2392.13Under implementation
2Construction of South Breakwater Extension, Groynes and Breakwater Toe Protection Wall at Paradip Port.508.52Under implementation
3Construction of 2nd exit road cum flyover at Paradip as part of additional Port connectivity from National Highway.93Under implementation
4A Road cum Flyover crossing the BOT Rail Tracks to have unobstructed access to the MCHP areas.35.23Under implementation
5Upgradation and modernization of Fishing Harbour at Paradip in Odisha.108.91Under implementation
6Construction of New Signal Station at Paradip.9.16Under implementation
7Construction of Retaining walls in the Stack yard (MCHP area).9.86Under implementation
8Construction and widening of Concrete Road, Retaining Walls etc. in harbour area.43.54Under implementation
9Development of Storage Plot near JSW Wagon Tippler inside Harbour area.9.11Under implementation
10Development of Plot near BOT Railway bulb and Gate No. 1 approach inside Harbour area.9.24Under implementation
11Mechanized Dust Suppression system for roads inside port prohibited area from Gate No.1 to Gate No.2.9.03Work Order issued on 04/10/2024
12MCHP-IOHP Connectivity (PMC Consultant M/s MECON)66.46 Crores inclusive of all taxes, duties & GST1st phase put into operation on dtd. 22/08/2020, 2nd phase project will be taken up on requirement.
13Supply, Installation , testing & commissioning of SCADA of Sub-stations of PPA.7.62Pre-commissioning work is going on. Out of 09 sub-stations, commissioning of 05 sub-stations have been established with MRSS. Commissioning of remaining 04 substations is under process.
14Design, fabrication, supply, erection and commissioning of Stacker - cum- Reclaimer of capacity 3000TPH.28.12Work completed on 18/06/2024
15Design, Engineering, Supply, Installation, Testing & Commissioning of shore to ship power supply facility at Coal Berth-I and Coal Berth-II at Paradip Port Authority on Turnkey basis.12.83Work Order issued on 12/07/2024 in favour of M/s Romas Electric Private Ltd. Bengaluru in JV with M/s. Danfoss Industries Pvt. Ltd. The firm has submitted the drawings and same has already been approved.
16Providing LT Power Supply to CB-I & CB-II.2.42Completion time of the work has been extended upto 18/11/2024. The approval of documents pertaining to HT & LT Cables submitted by the firm after change in make of cables, is under process.
17Supply, Laying Testing & Commissioning of HT / LT Cables at different locations of Paradip Port.2.71Cables already dispatched and yet reach at paradip Port.
18Supply, Installation, Testing & Commissioning of INDOOR type 11KV VCB ICOG standalone panels.1.03Installation of earthing has already been started. Drawing of panels approved.
19RFID Tender (5 years).10.40New tender to be floated , including AI/ML implementation after the scope of AI/ML is finalised.
20Hiring of 02 nos. of Truck mounted Mist cannons for a period of 05 years.3.91Work started w.e.f. 02/08/2024
21Hiring of 01 no. of Truck mounted Conveyorized Mechanical Road Sweeping Machine for a period of(03+02) years.6.61Work started w.e.f 24/06/2024
22Supply, Installation and Commissioning along with one year operation and maintenance of RFID based access control system Paradip Port Authority.1.72O & M Work completed and extended for a period of 03 months w.e.f. 17/09/2024

क्षमता संवर्धन परियोजनाएं संचालन में हैं

Sl. NoName of the ProjectStatus
1Development of Multi Purpose Berth to handle clean cargo including container at Paradip Port on BOT basis.
PA Operator : PICTPL
Cost : Rs. 430.78 Crores
Capacity : 5 MTPA
Terminal Operational.
2Development of New Iron Ore Berth for handling Iron Ore exports at paradip Port on BOT Basis.
PPA Operator : JSWPTPL
Cost : Rs. : 740.19 Crores
Capacity : 10 MTPA
Terminal Operational.
3Mechanization of EQ 1,2&3 berth at Paradip Port on BOT basis.
PPA Operator : PEQCTPL
Cost : Rs. : 1437.76 Crores
Capacity : 30 MTPA
Terminal Operational.
4Development of New Coal Berth for handling of Coal Imports at Paradip Port on BOT basis.
PPA Operator : KICTPPL
Cost : Rs. : 655.56 Crores
Capacity : 10 MTPA
Terminal Operational.

कार्यान्वयन के अधीन क्षमता संवर्धन परियोजनाएं

Sl. NoName of the ProjectStatus
1Deepening and optimisation of Inner Harbour Facilities including development of Western Dock on BOT basis to handle Capesize vessels at Paradip Port.Award of Concession issued to JPPL: on 17.10.2023. Project is under construction.

बंदरगाह संपर्क और अन्य परियोजनाएं

Sl. NoName of the ProjectStatus
1New Railway Line between Paradip-Haridaspur.

Rs.2700 Crores
This is a project implemented by Ministry of Railways. It has been completed on 12.08.2020 and it is operational
2Development of 2nd exit road cum flyover as part of additional Port connectivity for National Highway

Rs. 93 Crores
Under construction.

TDC: Q4 2022-23
3Numaligarh Refinery Limited Storage Terminal

Rs. 500 Crores
200 acres Land has been allotted to NRL.